Rio Americano High School

Paving

Rio Americano High School - Paving - After Project
Close Me!

Paving
After Project

  • Rio Americano High School - Paving - After Project

    Paving
    After Project

Project Overview

The scope of work for this project included:

  • multiple parking lot upgrades
  • hard-court repairs
  • fire-lane access
  • three interior courtyards
  • 2 breezeways

This project was a $640,000+ contract to be completed during the summer months while school was out. The Contractor accelerated their schedule and tried pouring all three courtyards in one day, not allowing enough manpower to follow behind and complete the finish before the concrete began to set and dry. Thus resulting in cracks due to missing expansion joints and un-repairable broom finish, causing the District to reject the work and requiring the Contractor to replace all three courtyards. By taking over 400 photos and collecting samples of the rejected concrete, ICS was able to document and demonstrate that the Contractor's work did not meet industry standards, therefore backing up the District's rejection of the work. ICS' CM was in the field all day, every day during the repair, and throughout the completion of the project for the opening day of school and did not cost the District a substantial amount of monies in claims, mediation, or litigation.

Completion Date: June 2009

Owner
Kent Kern
San Juan Unified School District
Sr. Director of Facilities
(916) 971-5796
Fair Oaks, CA   95628
USA
Architect
Joe Yee
Anova Architects
Phone: (530) 443-5911
Placerville, CA  95667
USA
IOR
Greg Estrada
UCI Inc
(209) 747-3544
PO Box 668
Clements, CA  95227
USA