Mesa Verde High School

New Gymnasium

Mesa Verde High School - New Gymnasium - Before Project
Close Me!

New Gymnasium
Before Project

  • Mesa Verde High School - New Gymnasium - Before Project

    New Gymnasium
    Before Project

  • Mesa Verde High School - New Gymnasium - During Project

    New Gymnasium
    After Project

Project Overview

Construction of New Gymnasium approximately 8,500 sq. ft. to include:

  • Retractable basketball back-stops;
  • Retractable bleacher seating;
  • Multi-use restroom facilities (Boys and Girls);
  • Hardwood gymnasium floor;
  • PE storage room;
  • Custodian room with mop-sink;
  • Stucco exterior with colored metal roof;
  • New side-walks and paving adjacent to building perimeter;
  • New utilities to building.

Construction began in Sept. 2008 and was completed on schedule and under budget.

This project was a Lease Leaseback Delivery Method. The value of the Lease Agreement was $3,217,764.00. Returned to the Owner of Unused/Saved project funds is $418,979.00.

Completion Date: June 2009

Owner
Kent Kern
San Juan Unified School District
Sr. Director of Facilities
(916) 971-5796
Fair Oaks, CA   95628
USA
Architect
Joe Yee
Anova Architects
Phone: (530) 443-5911
Placerville, CA  95667
USA
IOR
Bob Benson
(916) 997-2205