Mariemont Elementary School
Paving
Project Overview
The project scope included:
The contract amount for the project was $400,000 to be completed in 60 days. The project was on schedule when the Contractor uncovered the water main that had served the entire campus since 1958. Being the age and deterioration of the water main, the District required that the line be replaced. ICS directed and negotiated with the Contractor to complete this added scope with out affecting the contract end date milestone. “Based on the results of this year’s paving projects, ICS saved the District $1.2 million over the budget estimate. Excellent work!” -Don Myers |
Completion Date: August 2009
|