ICS Summer 2011 Highlights
Summer 2011 Sites
Dyer Kelly Landscape and Irrigation
![]()
Jonas Salk MS Landscape & Irrigation
![]()
Summer 2011 - Our Success Makes Us Different
24 Projects in summer 2011 with a total project value of over $13.2 million
- Average Change Order Percentage 2.99%
- Total Contract Value $13,296,708.00
- Construction completed in 56 days
- Projects include:
- 66 new trees planted.
- New high efficiency L.E.D. architectural parking lot lighting.
- New high efficiency irrigation water management systems with low maintenance, drought tolerant plantings, and decorative ground coverings.
- 120,000 sf of new concrete accessible walks.
Will Rogers "Green" Weight Room

Construction of 1,920 sf modular building built off site with a concrete slab on grade foundation. Scope of work included: grading, paving, foundation, and install of modular building. Building features include: matrix hardi-panel exterior, metal standing seam roof, and pin perforated metal interior ceiling. Building meets CHPS criteria.
Additional Sites include:
|
|
|